Fictional example · nothing is saved
Keep the agreement clear.
An original baseline, a later agreed programme and a live forecast can hold different dates.
| Task | Original agreed | Current agreed | Current forecast | Actual |
|---|---|---|---|---|
| First fix | 2026-09-18 → 2026-09-18 | 2026-09-24 → 2026-09-24 | 2026-09-25 → 2026-09-25 | 2026-09-25 → 2026-09-25 |
| Close walls | 2026-09-22 → 2026-09-23 | 2026-09-25 → 2026-09-28 | 2026-09-28 → 2026-09-29 | Not recorded → Not recorded |
Try issuing the current forecast for review
Review fixed proposal 3
Example reason: the first-fix completion moved by one day. These proposed dates stay fixed even if the working forecast changes later.
Working days: Monday, Tuesday, Wednesday, Thursday, Friday.
Closures: 2026-09-21.
| Task | Start → finish | Duration | Responsibility / notes |
|---|---|---|---|
| First fix work | 2026-09-25 → 2026-09-25 | 1 working day(s) | BuilderComplete the agreed first-fix scope. |
| Close walls work | 2026-09-28 → 2026-09-29 | 2 working day(s) | BuilderComplete the required checks before closing up. |
Dependencies (1)
- First fix → Close walls; 0 working-day lag.